Objective(s) i. To enhance the capacity of existing 132/33 kV substation;
ii. To increase reliability of power supply at Dhaka area and
Scope of Work 1. Ashuganj-Bhulta 400kV double circuit line: 69.00 km
2. LILO of Haripur-Rampura 230kV double circuit line at Bhulta Substation: 3.414 km
3. LILO of Ghorashal-Rampura 230kV double circuit line at Bhulta Substation: 1.10 km
4. Bhulta 400/230 kV 2x520 MVA AIS Substation
Project Cost Total: 107970.46 Lakh BDT, GoB: 14692.33 Lakh BDT, Project Aid: 77468.33 Lakh BDT, PGCB: 15809.80 Lakh BDT
Development Partner N/A
Duration July, 2014 to December, 2019

last updated on: 2025-07-02 10:50:10
Information Source: Project Planning