Objective(s) | 1) To evacuate the incoming generation of Power from the Meghanaghat Power Station. 2) To meet the growing demand of western part of Dhaka city. 3) To establish a reliable transmission network for Dhaka area. 4) To minimize transmission loss. |
Scope of Work | 400 kV Line: 54 km Double Circuit Bay Extension: 4 nos. (230 kV side) |
Project Cost | Total: 597.10 crore BDT, GoB: 145.45 crore BDT, PGCB: 181.33 crore BDT, PA: 270.32 crore BDT |
Development Partner | ADB |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | July, 2006 to June, 2014 |