Objective(s) | a) To extend High Voltage transmission infrastructure upto northern part of the country for import power in future from India, Nepal and Bhutan. b) To transmit the power from proposed 2x800 MW power plant to be built at Jharkhand, India by Adani Group. |
Scope of Work | a) Construction of Barapukuria-Bogura 400 kV Double Circuit Transmission Line: 120 km b) Construction of Bogura-Kaliakoir 400 kV Double Circuit Transmission Line: 140 km (including 9 km river crossing) c) Construction of 400 kV AIS Bay extension at Kaliakoir 400/230 kV Substation: 2 nos. d) Construction of 230 kV AIS Bay extension at Parbatipur 230 kV Switching Station: 2 nos. |
Project Cost | Total: 980583.56 Lakh BDT GOB: 284088.77 Lakh BDT PA: 620848.67 Lakh BDT PGCB: 75646.12 Lakh BDT |
Development Partner | EXIM Bank of India |
Present Status | Physical : 77.84 % Financial : 41.11 % |
Estimated Duration | January, 2019 to December, 2025 |
Project Office | Project Director : Mir Motahar Hossain, Chief Engineer, Addl. Charge Project Office : Power Grid Head Office Building, Aftabnagar, Dhaka-1212 Mobile : 01755511645 Email : pd.bbkp@pgcb.gov.bd |