Objective(s) | a) To establish a centralized coordination among generation, transmission & distribution of the existing power system. b) To operate each power station & substation at an economically profitable unit. c) To reduce operational loss. d) To save the electrical motors from being burnt out due to excessive variation in voltage &frequency. e)To improve communication between all the electrical installations in the existing power system through modern SCADA techniques &Communication network. |
Scope of Work | 1. SCADA System 2. Energy Management System (EMS) 3. Communication System |
Project Cost | Total: 421.68 crore BDT, GOB: 143.95 crore BDT, Project Aid: 277.73 crore BDT |
Development Partner | ADB |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | 2003-04 to 2009-10 |
Project Office |