Objective(s) | • To supply back feed power to upcoming 1st unit (660 MW) of Payra 1320 MW Power Plant by constructing 230kV line which will be used to make a transmission link between Payra coal power plant and adjacent area in future. |
Scope of Work | 1. To construct 47 km 230kV transmission line. 2. To construct 132 kV Switchyard (except transformer). 3. 132kV Bay Extension: 02 nos |
Project Cost | Total: 30535.05 Lakh BDT, GoB: 27960.68 Lakh BDT PGCB : 2574.37 Lakh BDT |
Development Partner | N/A |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | January,2017 to June, 2021 |