Objective(s) The main objective of the project is to create necessary facilities to evacuate power from upcoming coal based Payra 1320 MW Power Plant.
Scope of Work 1) Construction of Patuakhali (Payra) - Gopalganj 400 kV Double Circuit line: 163.43km
2) Construction of Line In Line Out (LILO) of Madaripur - Gopalganj (Old) 132 kV double circuit line at Gopalganj (New) substation: 11.87km
3) Construction of Line In Line Out (LILO) of Madaripur - Faridpur 132 kV double circuit line at Gopalganj (New) substation: 1.08km
4) Construction of Gopalganj 400/132 kV, 3x325 MVA AIS Substation
Project Cost Total: 248412.19 Lakh BDT PA: 208020.20 Lakh BDT GoB: 23721.26 Lakh BDT PGCB:16670.73 Lakh BDT
Development Partner ADB
Present Status Physical: 100.00 % Financial: 100.00%
Estimated Duration January, 2017 to June, 2023
Project Office Project Director : Md. Mamun Hasan, Chief Engineer (Addl Charge)
Project Office : NLDC Complex Bhaban, Aftabnagar, Badda, Dhaka- 1212
Mobile : 01730783335