Objective(s) i. To ensure reliable transmission of power generated in the Western Zone.
ii. To solve overloading problem of existing Goalpara-Bagerhat 132 kV line.
iii. To reduce transmission loss.
Scope of Work (1) About 45 km 132 kV double ckt. line including river crossing arrangement in four locations.
(2) One 132 kV bay Extension at Bagerhat.
(3) Replacement of bus conductor with higher capacity conductors at Bagerhat 132/33 kV substation.
Project Cost Total: BDT 89.2154 crore(PGCB), Local Currency (LC): BDT 45.0452 crore; Foreign Currency (FC): BDT 44.1702 crore
Development Partner -
Present Status Physical: 100%, Financial: 100%
Estimated Duration January, 2013 to June, 2016
Project Office

last updated on: 2020-12-30 05:57:00
Information Source: Project Planning