Objective(s) • To enhance the capacity of existing 132/33 kV substation;
• To supply the growing demand of the country.
• To ensure reliable power supply to rural area.
Scope of Work a) New 230/132/33 kV GIS substation: 01 no. (Total 3 x 225/300 MVA, 230/132 kV and 2 x 50/75 MVA, 132/33 kV)
b) New 132/33 kV AIS substation: 05 nos. (Total 10 x 50/75 MVA, 132/33 kV).
c) Capacity up-gradation of existing grid substations: 05 nos. (Total 10 x 50/75 MVA, 132/33 kV).
d) New 132 kV double Ckt. line: 82.472 Km
e) New 132 kV Single Ckt. line: 17.358 Km
f) 132 kV Double Ckt. Line in Line Out: 0.654 km
g) 132 kV Four Ckt. Re-routing and Interconnection: 6.932 km
h) 230 kV Double Ckt. Line in Line Out: 0.392 Km
i) Reconductoring of existing 132 kV double circuit line: 227 Km
j) Single circuit stringing of existing 132 kV double circuit line: 49.809 Km
k) OPGW stringing replacing earth wire of existing 132 kV line: 101.706 Km
l) New 132 kV Bay extensions at existing Grid substations: 5 nos.
33 kV AIS Switching Station for PBS (at 6nos. New Grid substation): 6 nos.
Project Cost Total: 107970.46 Lakh BDT, GoB: 14692.33 Lakh BDT, Project Aid: 77468.33 Lakh BDT, PGCB: 15809.80 Lakh BDT
Development Partner World Bank
Present Status Physical: 100%, Financial: 100%
Estimated Duration July, 2014 to June, 2021
Project Office

last updated on: 2021-07-04 03:35:50
Information Source: Project Planning