Objective(s) • To ensure reliable and uninterrupted power supply to Barguna and its neighboring areas.
Scope of Work a) Bakerganj-Barguna 132kV Single Circuit Stringing on double circuit towers:50.22 km
b) Construction of Barguna 132/33 kV AIS Substation: 2x50/75 MVA
Project Cost Total: 12313.79 Lakh BDT, GOB: 10853.73 Lakh BDT, PGCB: 1460.06 Lakh BDT
Development Partner N/A
Present Status Physical: 100%, Financial: 100%
Estimated Duration July, 2017 to June, 2021
Project Office

last updated on: 2021-07-04 09:40:47
Information Source: Project Planning