Objective(s) | • To evacuate power from the proposed 225 MW power plant at Sikalbaha; • Provide reliable power to Chattogram city through Rampur & Sikalbaha. • Meet the growing load demand all over the country through new eleven number of 132/33 kV substation. To Relieve the existing substation adjacent to the new substations. |
Scope of Work | a) Hathazari-Sikalbaha-Anowara 230 kV Double Circuit Line: 45 km b) Rampur-Agrabad 132kV Double Circuit Line U/G: 5 km c) Khulshi-Halishahar In-OUT 132kV U/G line Four Circuit: 3 km d) 132kV double Circuit Interconnection line: 131 km e) 132kV Loop-in loop-Out line: 8 km f) 2 number of 230/132 kV, 2x300 MVA (each) substation at Chittagong region g) 11 number of 132/33 kV substation all over the country (Total 2190 MVA). h) 230 kV Bay Extension: 4 Nos. 132kV Bay Extension: 9 Nos. |
Project Cost | Total: 242221.73 Lakh BDT,GoB:62432.79 Lakh BDT,Project Aid: 136650.00 Lakh BDT,PGCB:43138.94 Lakh BDT |
Development Partner | JICA |
Present Status | Physical: 100.00% Financial: 100.00% |
Estimated Duration | January, 2013 to June, 2022 |
Project Office | Project Director: Engr. Sukanto Lal Nag, Chief Engineer Address: 17 Mohakhali, Red Crescent Concord Tower (6th floor), Dhaka-1217. Mobile: 01714045696 E-mail: pd.nptndp@pgcb.gov.bd |