Objective(s) i. To evacuate power to be generated from Bibiyana power plant to national grid.
ii. To increase power supply stability, reliability, and transmission capability in Sylhet area.
Scope of Work a) Construction of 230 kV Switching Substation at Bibiyana
b) Construction of 230kV LILO (0.97km) line from Fenchuganj-Comilla (N) at Bibiyana Substation
Project Cost Total: 117.32 crore BDT(PGCB), LC: 75.75 crore BDT, FC: 5.35 m USD
Development Partner N/A
Present Status Physical: 100%, Financial: 100%
Estimated Duration June 2013 to June 2015
Project Office

last updated on: 2020-12-30 05:34:05
Information Source: Project Planning