Objective(s) | i. To evacuate power to be generated from Bibiyana power plant to national grid. ii. To increase power supply stability, reliability, and transmission capability in Sylhet area. |
Scope of Work | a) Construction of 230 kV Switching Substation at Bibiyana b) Construction of 230kV LILO (0.97km) line from Fenchuganj-Comilla (N) at Bibiyana Substation |
Project Cost | Total: 117.32 crore BDT(PGCB), LC: 75.75 crore BDT, FC: 5.35 m USD |
Development Partner | N/A |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | June 2013 to June 2015 |