Objective(s) | To create facilities to evacuate power from upcoming Matarbari 1200 MW Power Station and to create power transmission capacity/ facility between Matarbari and Madunaghat. |
Scope of Work | To construct 400kV transmission line-94.6 km. |
Project Cost | Total: 132304.00 Lakh BDT,GoB: 30906.00 Lakh BDT,Project Aid: 94858.00 Lakh BDT,PGCB: 6540.00 Lakh BDT |
Development Partner | JICA |
Present Status | Physical: 100.00% Financial: 100.00% |
Estimated Duration | July, 2017 to June, 2022 |
Project Office | Project Director : Md. Enamul Haque, Superintending Engineer Office : NLDC Building, 6th Floor, PGCB, Aftab Nagar, Merul Badda,Dhaka Mobile : 01730333265 E-mail : pd.mm400tlp@pgcb.gov.bd |