Objective(s) | 1) To ensure reliable transmission of generated power in greater Sylhet area. 2) To minimize overloading of existing Ashuganj-Shahjibazar 132 kV line. 3) To reduce transmission loss. |
Scope of Work | 1) 132 KV Line (53 km) from Ashuganj to Shahjibazar 2) 132 KV Bay Extension at Ashuganj,Sylhet, Shahjibazar, and Fenchuganj |
Project Cost | Total: 15.90 crore BDT |
Development Partner | N/A |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | 2007-08 to 2009-10 |