Objective(s) | i) To evacuate the surplus Power of Sylhet &Fenchuganj Area to the national grid. ii) To deliver more power to Comilla & Chittagong area from Sylhet. iii) To reduce the overloading of existing transmission lines in Sylhet & its adjacent area. iv) To relieve the existing "Ashuganj-Comilla 230 kV transmission line" from overloading. v) To reduce the transmission loss to some extent. |
Scope of Work | i) Construction of Bibiyana-Comilla (North) double Circuit 230 kV Transmission Line:153.632 km. ii) Construction of two nos. of 230 kV bay extension at existing Comilla (North) 230/132 kV Substation at 230kV side. |
Project Cost | Total: 369.50crore, GoB (FE): 229.95 crore, PGCB (FE): 139.55 crore |
Development Partner | N/A |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | Oct, 2010 to June, 2013 |
Project Office |