Objective(s) | i. To meet the growing power demand of western part of Dhaka city and to relieve the existing transmission network of the area ii. To enhance the reliability of power supply to the western part of Dhaka city. |
Scope of Work | 1) Aminbazar to Kallayanpur 230 kV Overhead Line 2) Kallyanpur to Old Airport 230 kV U/G Line 3) Old Airport to Dhaka University 132 kV U/G Line 4) Old Airport to Cantonment 132 kV U/G Line 5) Ullon to Rampura 132 kV U/G Line 6) Extension of 230/132 kV Substation at Aminbazar 7) 230/132 kV GIS Substation at Old-Airport 8) 132/33 kV GIS Substation at Dhaka University 9) 132/33 kV GIS Substation at Cantonment |
Project Cost | Total: 753.80 crore BDT, GOB: 222.331 crore BDT, PGCB : 50.997 crore BDT, PA : 61.60 m USD |
Development Partner | ADB |
Present Status | Physical: 100%, Financial: 100% |
Estimated Duration | August, 2006 to December, 2014 |
Project Office |