Objective(s) • To establish transmission infrastructure for evacuation of power to be generated from proposed power plants at Maheshkhali.
• To provide reliable power to all over the country.
Scope of Work 1. 765 kV Line
2. 400 kV bay extension
Project Cost Total Cost : 329,681.70 Lakh BDT
Development Partner EDCF.
Present Status PDPP was approved on 01/11/2015.
Estimated Duration July, 2026 to June, 2031
Project Office

last updated on: 2024-06-06 10:04:55
Information Source: Project Planning